捷運系統起重設備竣工檢查作業簡介 Introduction to the Examination Process of MRT Lifting Equipment
CU01-A7穿堂層起重設備安檢。

捷運系統起重設備之設置主要目的係提供環控設備及其他機電設備於進場安裝及未來維修吊運使用。此項設備除依照『勞工安全衛生法危險性機械及設備安全檢查規則』之規定委託代檢機構執行竣工檢查取得使用許可證外,並需於每兩年定期檢查一次以確保設備安全無虞。
國內有關起重設備之製造及使用均有國家制定之安全檢查標準,並經主管機關或其委託專業認證機構依此檢查標準驗證核可後核發使用許可證,捷運系統起重設備於設置完成時應填具固定式起重機竣工申請書,並向所在地檢查機構申請竣工檢查。
固定式起重機設備竣工檢查所需檢附文件:1. 製造設施型式檢查合格證明;2. 設置場所平面圖及基礎概要;3. 固定式起重機明細表;4. 強度計算及組配圖。
固定式起重機設備竣工檢查項目:
1. 構造與性能檢查:包括結構部分強度計算審查、尺寸、材料選用、吊升荷重審查、安全裝置之設置及性能、電氣及機械部分之檢查、施工方式、額定荷重及吊升荷重等重要標示、在無負載及額定荷重下各種裝置之運行速率檢測及其他必要之項目。
2. 荷重試驗:係將相當於該起重設備額定荷重1.25倍之重量,置於吊具上實施必要之吊升、直行、旋轉等重做試驗。
3. 安定性試驗:系將相當於該起重設備額定荷重1.27倍之重量置於吊具上,且使該起重設備於前方操作不利安定之條件下實施,並停止其逸走防止裝置、軌夾裝置等使用。
4. 其他必要之檢查。
竣工檢查合格之起重設備應將前項檢查合格證或其影本置掛於作業場所明顯處。

The purpose of installing MRT lifting equipment is to lift climate control equipment and other E&M equipment during installation and maintenance of the MRT system. Upon completing the installation, the consigned organization should evaluate the installed equipment based on "Safety Examination Regulation for Labor Safety & Health Law on Hazardous Machinery and Equipment" and retrieve its usage license. In addition, the equipment shall be periodically examined once in every two years to ensure operation safety.
Usage licenses can only be retrieved when the inspection results of the lifting equipment including manufacturing and usage processes conform to national safety standards and are verified by competent authorities or consigned professional verification organizations. After installation completion of the MRT Lifting Equipment, the application form for stationary crane installation completion should be filled out and be submitted to local examination organizations for formal examination.
Required documents for stationary crane installation completion examination are as follows:
1. Certification of manufactured module.
2. Surface plan and fundamental outline of installation venue.
3. Equipment composition list of stationary crane.
4. Calculation table of strength levels.
Examination items for stationary crane installation completion examination are as follows:
1. Structural and functional examination: structural strength calculation, measurements, material, lifting load inspection, installation and functionality of safety devices, electrical and mechanical inspections, construction method, major instruction signs of rated load and lifting load, operation speed of devices under zero and rated loading, and other required inspection items.
2. Loading tests: apply 1.25 times equivalent of rated load on the crane and perform lifting, straight, rotate and other actions.
3. Stability tests: apply 1.27 times equivalent of rated load on the crane and perform actions under adverse operating conditions. Additionally, runaway prevention devices and clipping devices are suspended during these tests.
4. Other required examinations.
After passing the examination tests, the certificate of qualification should be displayed in a prominent area in the workplace.

  • CU01-A7穿堂層通風井起重設備合格序號製作。