高鐵新增三站工程辦理情形簡介 Construction Progress Summary of the Three New HSR Additional Stations
高鐵雲林站主站體工程現況。

高鐵新增苗栗、彰化及雲林等三站屬高鐵後續工程計畫之工程,也是各車站所在地方之重大交通建設。本局除負責高鐵新增三站工程之施工監督外,同時亦協助辦理台灣高鐵公司與地方縣市政府間之介面協調工作。
高鐵新增三站皆屬高架型車站,其中高鐵苗栗站位於苗栗縣後龍鎮,其設計構想以「陽光」為出發點,形塑出車站輕巧造型,以簡單線條的金屬框架,營造多層次量體感,外牆並輔以垂直輕量化遮陽板,加深光影紋理與空間深度感,亦使立面更具多層次之韻律感;高鐵彰化站位於彰化縣田中鎮,「花卉」為建築表現的重要元素,大廳結構柱結合花卉意象,如花瓣薄翼般的開展造型,塑造出優雅的室內氛圍,站體內部設計植栽暖房,乘客在車站中可享受到濃郁的綠意,藉由通透、明亮、洗鍊的帷幕,呈現現代進步與快捷的想像;高鐵雲林站位於雲林縣虎尾鎮,設計造型運用「雲林」在地基調,並引入「虎斑」、「虎尾」意象,以37組姿態各異的巨型波浪柱列,架構流線型的車站建築。而站區廣場及綠地則種植大量喬木樹陣為「林」,而且還精心穿插佈置「雲」型線條的步道,充份展現「雲中之林」的在地風華。
高鐵新增三站除各站之站體結構及月台結構均已完成外,且均已於期限日內達成第二階段「完成全部外牆工程、屋頂排水暫時引至地面及與核心系統相關房間之建築、機電工程至先期完成程度,供核心系統界面承商進場施工及供鋪設核心系統線路所需之纜架工程,並提供設備機房臨時用電及空調」之契約里程碑,目前正趲趕第三階段與台電公司送電相關房間之建築、機電工程及機電設施之單機運轉、測試,暨送電至各核心系統線路界面點之契約里程碑工程。其他相關建築裝修、水電環控、外部及景觀工程亦持續趕工中,預訂於104年7月完工。

The constructions of HSR Miaoli, Changhua and Yunlin are part of the HSR Subsequent Project and are also the major transport infrastructures of local areas. In addition to playing the role as supervisor for the three constructions, BOHSR also acts as the interface coordinator between THSRC and local authorities.
The three new HSR stations were all designed as elevated stations. HSR Miaoli Station is located at Houlong Township, Miaoli County. The station design constructed a lightweight station revolving around the concept "sunshine". The design used simple linear metal frames to form multilayer visual effects. In addition, vertical lightweight shades were applied on external walls to produce lighting and shadow effects, deepen a spatial visual experience and increase rhythmic patterns on the wall. HSR Changhua Station is located in Tienchung Township, Changhua County and the station design used "flowers" as its significant element. Floral concepts are applied in the lobby structural piers using a petal-like flourishing visual design to bring out an elegant interior atmosphere. Additionally, a greenhouse is installed inside the station along with transparent and bright curtains for passengers to enjoy the green ambience and acknowledge the modern and rapid concepts all during a walk through the station. As for HSR Yunlin Station, it is located in Huwei Township, Yunlin County. Using the Chinese definition of the station name, "Yunlin" and "Huwei" (meaning "clouds and forest" and "tiger's tail"), as its design concept, the fluent station architecture consisted of 37 different giant wave piers. In the station plaza and surrounding ground, trees are planted representing "Lin" (English meaning: forest) and "cloud-like" trails crossing the trees are installed representing "Yun".
Summarizing the construction progress of these three additional HSR stations, station structures and platform structures are all finished and have all achieved completion of Stage 2 construction before deadline. Currently, the constructions are under Stage 3, including construction of power distribution room, operation and testing of E&M engineering and relevant facilities, and core system interfaces of power distribution from Taipower Company. The Electrical Systems & Water Services and Environment Control, external constructions and landscape designs are also under tight progress striving to reach construction completion by July 2015.

  • 高鐵彰化站主站體工程現況。
  • 苗栗站月台層雨庇鋼柱包版骨架及月台地磚施作現況。
  • 彰化站主站體大廳花朵柱外觀修飾乙景。
  • 雲林站西測站體外牆金屬包鈑完成外觀。
  • 高鐵苗栗站主站體工程現況。