機場捷運電(扶)梯設備使用許可申辦簡介 Introduction to the Usage Permit Application of TIAA MRT Elevatiors and Escalators
機場捷運新莊副都心站電扶梯實景。

機場捷運各電(扶)梯設備安裝完成後,除由專業廠商自我調校及檢測外,仍需經過第三方或認可之專業檢查單位進行文件檢核及實機測試,始可取得各電(扶)梯設備專屬的使用許可證明。以下就電(扶)梯設備使用許可申辦程序概略說明:
電(扶)梯設備於安裝完成辦理竣工檢查後,依契約規定由廠商向地方主管建築機關或檢查機構申請使用許可。應備文件包括建築物昇降設備竣工檢查申請書、特種建築物免建照函影本、強度計算書、試驗報告及建築物昇降設備圖等,待審查合格後寄發竣工檢查通知書,並依申請順序及設備數量,排定檢查日期,如經檢查均屬合格,始核發有效期一年之建築物昇降設備使用許可證,且一機一證。
至於使用許可申辦時機,通常於通車前二個月辦理較佳,如實質完工日與營運日差距過大,則需另行協商昇降設備之竣工檢查日期,以使電(扶)梯設備運轉日期與通車日期儘量接近。

To obtain the exclusive usage permit certification, the installed elevators and escalators shall not only be calibrated the supplier but also has to be tested and documentation-verified by a certified third party organization. The application procedures to obtain the exclusive user permit certification are briefed as follows:
When the elevating equipment is finished with installation and completed with required testing, the supplier shall apply to the local competent building authority or inspection organization for usage permit. Application papers include elevating equipment inspection application form, a copy of building exemption certificate for special building type (SBT), intensity calculation report, test reports, elevating equipment graphics, etc. After all documentations are qualified, the inspection dates, application procedures and equipment quantity will be arranged according to the formal inspection notice. Upon qualification of onsite inspection, the one-year effective usage permit certificate will then be issued. In addition, the elevating equipment usage permit certificate is issued one per equipment.
As for the timing for application, the whole process should be implemented before two months of scheduled official operation. Supposing the period between actual construction completion date and official operation date is too long, the inspection date of elevators and escalators should be coordinated to be as near to the official operation date as possible.