臺中捷運系統烏日文心北屯線建設計畫辦理情形 Implementation Status of the Taichung Metropolitan MRT System Wurih-Wunsing-Beitun Line Construction Project
臺中捷運系統烏日文心北屯線計畫路線圖。

臺中捷運系統烏日文心北屯線採高架方式佈設,自北屯區松竹路、北屯路、文心路、文心南路至烏日高鐵臺中站,設置18座車站,1座機廠,全長約16.71公里,高架段約15.94公里,地面段約0.77公里,計畫總經費513.9億元(含用地經費)。
民國88年間,交通部承接原臺灣省政府移撥省轄都會區捷運建設計畫推動作業,於本局完成臺中捷運烏日文心北屯線計畫規劃報告後,因考量地方捷運建設推動需求及充分運用臺北市政府捷運工程局人力資源,交通部依大眾捷運法委託臺北市政府辦理後續設計、施工等事項,由臺北市政府捷運工程局負責進度控管、年度預算執行之控管與績效。
本計畫所有工程均已發包,核心機電系統於100年4月21日開工,正辦理細部設計,土建工程3個標案於102年起陸續開工,然因歷經機電系統統包工程3次流標,以及臺中市政府辦理用地取得時程落後,依臺北市政府捷運工程局提報之進度,至104年4月底止,預定進度71.54%,實際進度60.11%,落後11.43%,修正計畫已於104年4月1日陳報行政院,全線預計於109年底通車。

The Taichung Metropolitan MRT System Wurih-Wunsing-Beitun Line will adopt an elevated system starting from Songzhu Rd. (Beitun Dist.) crossing Beitun Rd., Wenxin Rd., Wenxin S. Rd. to HSR Taichung Station in Wuri District. The total length of this system will be 16.71km with the elevated sections of 15.94km and surface sections of 0.77km. Total budget of this project is 51.39 billion NT dollars (inclusive of land fees).
In 1999, MOTC took on the construction project of Promoting the Provincial Metropolitan Area MRT (Mass Rapid Transit) that was originally managed by Taiwan Provincial Government. After completion of project planning, BOHSR transferred authority to DORTS. Hereafter, based on Mass Rapid Transit Law, MOTC entrusted Taipei City Government to implement subsequent designing and construction processes and DORTS to be responsible for progress monitoring and annual budget control.
All constructions in this project have completed contracting in which the core E&M systems have broken ground on Apr. 21, 2011 and is currently working on detail designs; the three civil engineering tenders have successively started since 2013. However, due to three failing tenders for E&M bundle constructions and the delay of land acquisition by Taichung City Government, DORTS reported that up until April 2015, scheduled progress is 71.54% and actual progress is 60.11%, creating a 11.43% delay. The revision plan has been submitted to Executive Yuan on Apr. 1, 2015 indicating full operation scheduled by end of 2020.