高鐵新增三站完成竣工檢查 Project Completion Inspection on the Three Additional HSR Stations
胡局長主持雲林站標竣工檢查總結會議

高鐵新增雲林、苗栗及彰化車站已於104年6月23日陸續完工,本局依據「台灣南北高速鐵路後續工程竣工檢查實施計畫」自104年6月26日起至104年8月5日止,對高鐵新增3站辦理竣工檢查。
各站辦理竣工檢查時間,苗栗站於104年7月15日、20日辦理完成、彰化站於104年8月3日、5日辦理完成、雲林站於104年6月26日、28日辦理完成,檢查人員分為車站組、核心機電組及營運設施組等三組,按各組權管會同技術顧問辦理檢查作業,檢查範圍為各站(含界面整合)的竣工作業辦理情形,包含文件檢查、實地勘查及相關缺失改善情形。檢查所發現之應行改進事項,依其影響性,區分為「影響重要設備事項」及「一般性事項」等二類。
台灣高鐵公司於各站之應行改進事項辦理改善後,向本局提出複查申請,本局旋即於104年8月18日及31日辦理新增3站複查作業,確認各站屬於影響重要設備事項均已改善完成,同意結案,另屬一般性事項未完成部分,由台灣高鐵公司繼續辦理改善中。各站應行改進事項辦理情形,經複查更新後統計如附表。

In view of the completion of the three additional stations, Yunlin, Changhua and Miaoli, by June 23, 2015, BOHSR has been getting down to implementing the project completion inspection from Jun. 26 to Aug. 5, 2015 according to the "Implementation Plan of Taiwan North-south High Speed Rail Follow-up Construction-completed Inspections".
The respective inspections have been conducted on Jul. 15 & 20 for Miaoli Station, Aug. 3 & 5 for Changhua Station and Jun. 26 & 28 for Yunlin Station. The inspectors were divided into three groups, station group, core electrical & mechanical facilities group and operational equipment group. The inspections were carried out with the supervision of group authorities and technical consultant. The scope of the inspections (including interface integration) contained document evaluation, field surveys and relevant improvement measures. The improvement measures were classified based on its correspondence impact level into" Significant Equipment- Affected Item" and "General Item".
After making the improvements at each station based on the inspection results, THSRC applied for secondary inspection. Hence, BOHSR arranged the three inspections on Aug. 18 and 31, 2015 to ensure that the improvement measures were actually executed and approved for project conclusion. As for the unfinished general items, THSRC is currently implementing improvement measures.Subsequent to the secondary inspection, the status of awaiting improvement items are updated as follows.