機場捷運青埔機廠水電環控工程施工現況 Construction Status of Electrical & Water Services and Environment Control Construction of TIAA MRT Project's Chingpu Depot
青埔機廠行控中心冰水泵浦。

機場捷運設有青埔及蘆竹兩個維修機廠,分別為五級之主維修廠及三級之副維修廠。其中,青埔機廠(含A17站)佔地約18.6公頃,基地位於高鐵桃園車站特定區東北側,領航北路及高鐵北路交叉口,北臨新街溪,其水電環控工程概分為機械、電氣、環控、電梯、起重機等主要工程,截至102年底已大致施工完成。
1.機械工程:包括給水系統、排水系統及消防系統等3項。
2.電氣工程:包括低壓配電系統、不斷電系統、照明系統、接地及避雷系統、火警偵測系統、緊急廣播系統、公共電話及閉路電視系統等8項。
3.環控工程:包括空調、通風及排煙系統等3項,目前正施作風機、風口移位及增設自然排煙窗等。
4.電梯:包括客用、貨用及客貨兩用等3項。
5.起重機:包括主變電站、主維修廠及固定設施維修廠等之起重機等。
青埔機廠施工廠商已初步完成水電環控工程之單機測試,預計103年1月申請消防會勘,之後將全面展開系統及整體相關測試作業。

The TIAA MRT Project is equipped with two maintenance depots, respectively the fifth-grade main depot Chingpu Depot and third-grade secondary depot Lijhu Depot. The Chingpu Depot base stands at the northeast side of HSR Taoyuan Station District with a total floor space of 18.6 hectares. The exact location is at the intersection of Linghang North Rd. and Gaotie North Rd.which is just south of Hsinjie River. The contents of Electrical & Water Services and Environment Control Construction include mechanical construction, electrical construction, environment control construction, elevators and cranes. The construction is almost done by the end of 2013:
1.Mechanical Construction: include 3 items, the Water Supply System, Drainage System and Fire Protection System.
2.Electrical Construction: include 8 items, the L.V. Power Distribution System, UPS System, Lighting System, Grounding System, Fire Detector System, Emergency Broadcasting System, Public Telephones and Closed Circuit Television (CCTV) System. The 8 items were all completed by end of December 2013.
3.Environment Control Construction: include 3 items, Air Conditioning System, Ventilation System and Smoke Extraction System. Current construction is at the ventilation fan, moving of the ventilation shaft and installing natural smoke extract window.
4.Elevator Construction: include 3 items, the Passenger Elevators, Freight Elevators and Passenger/ Freight Elevators.
5.Crane Construction: include the cranes of Main Bulk Supply Substation, Main Maintenance Depot and Stationary Equipment Maintenance Workshop. All cranes were completely Contractors have already run initial tests on the constructions. From January 2014 on, Fire Protection Review will be scheduled and the following system integration tests will be executed soon after.