Newsletter 高速鐵路簡訊 . 交通部高速鐵路工程局
「臺中都會區鐵路高架捷運化計畫」第一階段履勘作業紀要 Summary of the First Phase Inspection of “Taichung Metropolitan Area Elevated Railway Project”
履勘小組進行現場勘查。

鐵路運輸系統營運前,應依鐵路法第16條第2項規定,向交通部提出履勘申請,經核准後,始得營運。本局配合交通部鐵路營運監理小組擔任履勘工作分組成員協助辦理履勘幕僚作業。
履勘小組設召集人、副召集人各1名,下設土建、機電、營運等3組。召集人依慣例由交通部路政司司長擔任並兼當然委員,統籌辦理履勘作業相關事宜。副召集人由土建、機電、營運等3組組長互選推派。
交通部臺灣鐵路管理局於105年6月29日提出「臺中都會區鐵路高架捷運化建設計畫」第一階段通車履勘申請。本階段通車範圍為:北起豐原站以北約1.9公里,南迄大慶站以南約1.4 公里,全長約21.7公里,項目包括:臺中站、豐原站、潭子站、太原站、大慶站暨沿線鐵路高架路段。本案續於105年7月14日對申請單位進行文件形式審查及確認受檢資料狀況,於105年7月27日召開履勘前置會議,並於105年8月23至24日辦理履勘作業。
履勘委員針對受檢單位所備文件、現地設備設施以及模擬演練等勘查項目,檢視後提出28項相關缺失與建議。其缺失改善事項共分為3類,其中「營運前須改善事項」10項,須備妥相關改善證明文件報部,獲核准後方得通車營運。「一般注意改善事項」7項,則由鐵路營運監理小組追蹤改善情形至完成結案;至於「後續建議改善事項」11項,則請受檢單位辦理後續工程或改善設施時參考辦理。在履勘小組、工作分組及受檢單位等單位充分配合下已順利完成本次履勘作業。

According to Article 16.2 in Railway Act, the railway organization is required to apply for MOTC pre-operation inspection before official operation and can only operate after acquisition of MOTC approval. In coordination with Railways Supervision Task Force, BOHSR took post as inspectors to assist in advising work.
The inspection team comprised of one Convener, one Vice Convener, a civil engineering group, an E&M group and an operation group. The Convener as well as ex-officio member was chosen by convention to be the Director General Department of Railways and Highway, MOTC and is responsible for integrating all inspection-related matters. The Vice Convener was elected among the heads of the three groups.
On Jun. 29, 2016, TRA of MOTC submitted the inspection application of the first phase operation of “Taichung Metropolitan Area Elevated Railway Project”. The scope of the operation extends 21.7 kilometers which covers from 1.9 kilometers north of Fengyuan Station to 1.4 kilometers south of Daqing Station. The project includes Taichung Station, Fengyuan Station, Tanzi Station, Taiyuan Station, Daqing Station and all elevated sections along the railway. On Jul. 14, 2016, the inspection team implemented formality examinations and verified the application documents. By Jul. 27, the inspection preliminary meeting was called for and the actual inspection operations took place from Aug. 23 to 24, 2016.
The inspectors raised 28 improvement points according to evaluation results of documentation, on-scene equipment and simulation practices. The improvement points were categorized into 3 categories. 10 of the improvement points were categorized as pre-operation matters in which the railway organization has to submit all necessary documents to MOTC to be cleared for operation; 7 points that were general matters will be followed up by Railways Supervision Task Force until all improvement points are achieved; and for the 11 follow-up suggestions, inspected unit will take into consideration for future engineering projects. With great efforts and cooperation of all participating parties, the inspection work was finished.

  • 現場模擬演練情形。
  • 分享: