105年度阿里山森林鐵路定期檢查辦理紀要 2016 Alishan Forest Railway Annual Inspection
105年度阿里山森林鐵路定期檢查之路線檢查。

本局配合交通部鐵路營運監理小組於105年11月2日至3日執行105年度阿里山森林鐵路定期檢查作業。本次檢查係依據鐵路法第41條及「地方營民營及專用鐵路監督實施辦法」第47條規定辦理。檢查事項包括「組織狀況」、「營運狀況」、「財務狀況」、「工程狀況」、「行車安全管理」、「機車、車輛檢修狀況」、「路線修建養護狀況」及「其他有關事項」等8大類,計24項檢查項目,分別由營運、土建、機電等3類分組進行重點查察作業。
年度定期檢查由呂副總工程司新喜率相關檢查同仁赴農委會林務局嘉義林管處聽取簡報,除檢視現行組織、規章、制度、相關管理程序及營運路線執行情形,並抽檢實際作業報表與紀錄等文件。另由於本年7月份監理小組配合交通部辦理「阿里山森林鐵路奮起湖至十字路段暨屏遮那至神木段」復駛臨時檢查,爰本次檢查一併查察沿線各路段改善辦理情形與復駛營運前準備狀況,並特別排定檢視104年至105年9月間發生行車事故事件地點、重要車站、隧道、車庫及高風險路段等場所進行現勘及路線巡檢作業,以瞭解實務運作情形,期能透過各面向的檢查作業,精進森鐵各項安全管理措施,俾強化森林鐵路行車安全。

In accordance with the Railways Supervision Task Force of MOTC, BOHSR implemented the 2016 Alishan Forest Railway Annual Inspection from Nov. 2 to 3, 2016. The inspection was conducted based on Article 41 of Railway Law and Article 47 of Regulations Governing Supervision of Local, Private, and Exclusive Railways. The eight major inspection items included Organization, Operational Situation, Financial Situation, Constructions, Safety Management System, Maintenance of Trains, Maintenance of Tracks and Others. There were a total of 24 inspected items, which were respectively implemented by Operations, Civil Engineering and E&M Divisions.
The annual inspection was led by Deputy Chief Engineer Hsin-Hsi Lu with relevant associates and first arrived at Chiayi Forest District Office of Forestry Bureau for briefing. The inspectors not only evaluated the implementation of current organization, regulations, systems, relevant managing procedures and operational routes but also randomly reviewed actual working logs and records. Additionally, due to the extempore investigation on "Alishan Forest Railway Restoration Project-Fenchihu to Shizilu and Pingzhena to Sacred Tree" that was implemented by Railways Supervision Task Force, the inspectors especially evaluated the current restoration status and pre-operation situation of this section. The inspectors also arranged on-site inspections and route evaluations at accident sites that happened during 2015 to Sep. 2016, major stations, tunnels, garages and high-risk sections to comprehend with operational details. The inspection party anticipated that with this comprehensive inspection, safety management measures will be improved ultimately enhancing operational safety of the forest railway.

  • 44K隧道口落石崩落現地勘查。
  • 第33號平交道事故現地勘查。
  • 66K彎道處工程車翻覆現地勘查。