機場捷運CU03標土建工程部分驗收準備作業 Preliminary Work for Civil Engineering Construction Acceptance of TIAA MRT CU03 Tender
CU03標現場初驗情形

機場捷運CU03標包括出土段約350公尺、高速公路既有涵洞內水環工程約75公尺、明挖覆蓋隧道約282公尺,及環北站(A21)地下車站土建、水環、建築裝修約182公尺,已於103年1月辦理水環工程以外之土建工程部分驗收初驗工作,預定於103年4月辦理複驗,率先啟動機場捷運各標工程之驗收作業。
承包商大成工程股份有限公司依契約一般條款補充規定,於102年11月22日建請同意辦理本部分驗收,驗收範圍為土建工程所有工作項目,案經監造單位102年11月25日核轉本局捷運工程處,獲該工程處同意於A21車站取得消防安全設備查驗核可證明後辦理。
承包商於102年11月27日取得A21車站消防安全設備查驗核可證明,旋以該核可文號日期102年11月19日為土建工程竣工日,並提送「工程竣工報告表」。經監造單位及捷運工程處中壢工務所分別召開「土建工程竣工確認會議」後,確認已依契約規定完成土建工程。捷運工程處於102年12月11日核定「工程竣工報告表」,並經陳報本局同意後,該工程處隨即辦理相關簽核作業,並如期辦理土建工程竣工之部分驗收初驗,預定於103年4月辦理複驗。

The TIAA MRT CU03 Tender includes 350 m daylighting section, 75 m electrical systems & water services and environment control construction in the original highway culvert, 282 m cut-and-cover tunnel construction, 182 m of the civil engineering, electrical systems & water services and environment control construction, architectural renovation of the underground Huanbei Station (A21). The civil engineering constructions excluding the electrical systems & water services and environment control part have proceeded to the initial stage of acceptance in Jan 2014. The second stage of acceptance is scheduled to take place in Apr. 2014 making Tender CU03 the first TIAA MRT construction tender to proceed with acceptance procedures.
According to contract supplementary terms, the contractor Ta-Chen Construction & Engineering Corp. suggested partial acceptance to be conducted on Nov. 22 2013. The partial acceptance included all items in the civil engineering category. The tender was transferred to MRT Engineering Office, BOHSR by the original supervision unit on Nov. 25 2013 and was approved to proceed with acceptance after fire protection facilities in A21 Station were installed and officially authorized.
The contractor retrieved the fire protection facility authorization certificate on Nov. 27 2013 and used the certificate-authorized date, Nov. 19 2013, as the civil engineering construction completion date. The contractor submitted the "Construction Completion Report" accordingly to its supervision unit and Zhongli Branch of MRT Engineering Office for recognition. After holding "Civil Engineering Construction Completion Verification Meeting" by both authorities, the civil engineering construction was confirmed to be finished according to contract. MRT Engineering Office officially ratified the "Construction Completion Report" on Dec. 11 2013 and conducted its acceptance procedures accordingly with BOHSR's approval. The civil engineering constructions successfully proceeded with initial acceptance as planned and are scheduled to further proceed with the second stage of acceptance in April 2014.