機場捷運核准營運通車 TIAA MRT System Approved of Operation
機場捷營核准營運通車記者會照片。

機場捷運工程已完竣並具備通車營運條件,由高鐵局於105年12月3日、4日辦理初勘作業完成改善後,交通部於105年12月29日、30日辦理履勘作業。履勘結果要求之「營運前須改善事項」,高鐵局已完成改善,並經履勘委員確認,交通部於106年1月25日依法核准營運通車。
桃園市政府為機場捷運地方主管機關,交通部核准營運後,在桃園市政府督導下,由桃園捷運公司接手後續營運事宜,並自106年2月2日啟動為期一個月之試營運,試營運分為兩階段,前2周為團體受邀試乘階段;後2周為民眾憑號碼牌自由試乘階段,並規劃自3月2日起正式營運。相信在桃園捷運公司努力下,一定能提供民眾前往桃園機場,以及沿線臺北市、新北市、桃園市民眾通勤之安全、舒適、便捷的優質服務。
按機場捷運合約規定,依法完成通車程序後,尚需依照合約標準進行為期一年的機電系統可靠度、可用度、維修度及安全性(RAMS)驗證展示,通過後方得申報竣工及驗收。因此,機場捷運通車後,依合約規定須改善部分,高鐵局將要求廠商持續改善,達到契約規定標準後才驗收。

The TIAA MRT Project has been completed and is equipped with all the operation conditions. After resolving improvement issues of the initial inspection on Dec. 3 to 4, 2016, MOTC implemented the final inspection on Dec. 29 to 30, 2016. BOHSR has completed the improve-ment issues that needed to be improved before operation and has been confirmed by inspection members. In consequence, MOTC approved of operation of the TIAA MRT System on Jan. 25, 2017.
Taoyuan City Government is the local competent authority for TIAA MRT, so after approval from the MOTC, the system will be managed and operated by Taoyuan Metro and supervised by Taoyuan City Government. On Feb. 2, the one-month service trials program was initiated and is divided into two phases. The first two weeks will be the trial run phase for invited groups; the last two weeks will be the free trial run phase open to the public in which the people can ride the train with a reserved number. On Mar. 2, official operation will be initiated. We believe in the efforts of Taoyuan Metro, the TIAA MRT will be able to provide safe, comfortable and convenient quality service to people traveling to Taoyuan Airport as well as commuters along the Taipei City, New Taipei City and Taoyuan City commuting line.
According to the TIAA MRT contract, the system has to pass a one-year demonstration on the reliability, availability, maintenance and safety RAMS validation of the E&M system after completing operation procedures in order to apply for construction completion and acceptance. Therefore, BOHSR will ask contractors to implement continuous improvements after the opening of the system to achieve regulated standards in order to be complete acceptance procedures.