Newsletter 高速鐵路簡訊 . 交通部高速鐵路工程局
機場捷運延伸線CM01區段標交通部工程施工查核紀要 Summary of the MOTC Construction Inspection on the TIAA MRT Extension Line CM01 Section Tender

機場捷運CM01區段標交通部工程施工查核作業,於106年3月15日上午假高鐵局捷運工程處中壢工務所會議室辦理,由交通部路政司重大工程督導會報李技監兼執行秘書泰興率交通部工程施工查核小組辦理CM01區段標工程施工查核。會議中由施工督導單位進行工程簡報,簡報內容簡單扼要說明工程執行現況、三級品管制度檢查辦理情形,及品質、安衛作業抽(檢)查缺失改善及追蹤辦理情形。再由承包商說明目前施作工項並就現地查核停留點及動線提出建議,在安衛人員辦理危害告知作業後即著裝進行現地查核作業。
現地查核由承包商現場簡報施工現況並視察工區第三層開挖及支撐架設作業,隨後前往A22車站工區,視察車站及潛盾隧道北工作井,並進行鋼筋材料抽樣試驗,現場查核委員以豐富之工程經驗對各項施工內容提問,施工團隊皆能逐一答覆並與查核委員熱烈討論,互相交流。
本次施工查核總結會議,各查核委員對於CM01區段標工區安全衛生、環境整理、施工動線安排及混凝土完成面施工品質等多所肯定。另對於查核委員針對現場部分施工及自主檢查文件的改善建議,施工團隊回應感謝委員的指導與建議,並立即配合改善,以求更進一步提升工程品質。
本次交通部工程施工查核時程緊湊內容豐富,最終CM01區段標工程獲得甲等(不扣點)的查核佳績,未來將持續精益求精以提升工程品質。

The MOTC construction inspection on the TIAA MRT CM01 section tender took place in the morning of Mar. 15, 2017 in the conference room of Zhongli branch, MRT Engineering Office. The construction inspection of CM01 section tender was led by Technical Superintendent/Executive Secretary Tai-Shin Lee of Major Construction Supervision Task Force, Department of Railways and Highways, MOTC with the construction inspection team. The meeting started with a briefing by Chief Hsin-Huang Wu of Zhongli Branch, MRT Engineering Office on the execution status, three-tier quality control inspection status and the fault improvement & tracking status of quality and safety random check operations. Then, the contractor elaborated on the currently constructing items and proposed suggestions on the stopping points and route of the onsite inspection. Subsequent to hazard notification implemented by the EHS staff, the inspectors dressed up and initiated onsite inspecting operations.
During the onsite inspection, the contractor did a briefing at the construction site and then the inspection on the third-layer excavation and supporting operations was carried out. Following, the party went to the construction site of A22 Station to inspect the station and north shaft of the shield tunnel and to collect steel material samples for testing. Enriched with experience in engineering, inspectors raised questions regarding matters of the construction. Relatively, the construction team addressed the questions one by one and discussed and exchanged ideas with the inspection members.
In the conclusion meeting of the construction inspection, the inspection members affirmed of the safety and health, environmental consolidation, construction route of the site, the quality of the completed concrete construction and other aspects of the CM01 section tender construction. This showed good results of the construction quality made by joint efforts from the construction owners, supervision and contractors. On the other hand, the construction team thanked inspectors for the instructions and suggestions regarding certain parts of the construction and self-inspected documents and will implement immediate improvement in order to further enhance the quality of the project.
In this MOTC construction inspection, the schedule was compact and was rich in content. In the end, the construction project obtained an “A” (no point deduction) in the inspection. In the future, the construction team will continue to strive to improve the quality of the project.

  • 分享: