機場捷運初履勘作業缺失改善事項辦理情形 Implementation Status of the Improvement Issues from TIAA MRT Initial Inspection and Final Inspection
全線號誌設備調整、更換作業。

機場捷運於105年12月3日至4日完成初勘檢查,其中初勘評定結果之12項「履勘前須改善完成事項」業於12月15日確認完成改善,並報請交通部辦理履勘檢查;交通部於105年12月29日至30日完成履勘檢查,後續履勘評定結果之8項「營運前須改善事項」,則由本局所屬捷運工程處暨相關施工單位會同營運單位桃園捷運公司、桃園機場公司於106年1月20日完成改善並經履勘委員確認,交通部於106年1月25日依法核准營運通車。
檢查所列「初勘一般注意改善事項」49項及「履勘一般注意改善事項」36項,交通部已責成本局專案列管辦理改善,本局自106年1月12日起定期召開專案會議追蹤檢討相關改善事項辦理情形,截至106年3月底,「初勘一般注意改善事項」包含各月台邊增設膠條改善間距過大情形及號誌設備調整、更換作業在內,已完成44項改善,「履勘一般注意改善事項」包含全線各車站清潔及機房地板高低差處加設警示色帶在內,已完成31項改善。

The initial inspection was completed on Dec. 3 to 4, 2016. Initial inspection results included 12 improvement issues that needed to be improved before final inspection. The issues have been addressed by Dec. 15, 2016 and submitted to MOTC for final inspection. The final inspection was completed on Dec. 29 to 30, 2016. The inspection results included 8 improvement issues that needed to be improved before operation. Those issues needed to be improved before operation have been resolved by MRT Engineering Office and relevant construction units together with Taoyuan Metro and Taoyuan Airport Corp. on Jan. 20, 2017 and has been confirmed by final inspectors. On Jan. 25, MOTC approved of operation in accordance with the Mass Rapid Transit Law.
The 49 “general issues in initial inspection” and 36 “general issues in final inspection” MOTC has appointed BOHSR to be responsible for project management and improvement. Since Jan. 12, 2017, BOHSR held regular ad hoc meetings to review the relevant improvement issues. As of the end of March, 2017, 44 “general issues in initial inspection” including improving spacing between the tape alongside each side of the platform and signaling equipment adjustment and replacement operations have been resolved. As for the “general issues in final inspection” including cleaning operations of all stations and adding warning tape for floor height difference at the data stations, 31 issues have been resolved.

  • 機房地板高低差處加設警示色帶。
  • 全線各車站清潔作業。
  • 各月台門邊增設膠條。