機場捷運土建標全標竣工(最終)驗收作業 Final Acceptance Operations for the TIAA MRT Civil Engineering Construction Tenders
機場捷運CE03B標全標竣工(最終)驗收。

機場捷運CE01B、CE01C、CE01D、CU01、CE02、CU02、CE03A、CE03B、CU03等9個土建施工標前於105年1月28日完成配合機電系統之營運前試車支援工作後提報竣工,俟各標廠商依契約規定備齊完整竣工文件及歷次部分驗收成果文件資料,已陸續提報本局捷工處完成全標竣工(最終)驗收之初驗作業。
本局收到捷工處所提CU03標全標竣工(最終)驗收之初驗資料,於本(106)年3月30日開始辦理第一個土建標全標竣工(最終)驗收工作,並於驗收合格後簽發「工程結算驗收証明書」予承包商,其餘各標俟捷工處完成初驗後,提報本局辦理最終驗收事宜,預計本(106)年下半年完成所有土建標全標竣工(最終)驗收作業。

Nine of the civil engineering construction tenders, CE01B, CE01C, CE01D, CU01, CE02, CU02, CE03A, CE03B and CU03, have completed the pre-revenue service support by Jan. 28, 2016 and submitted for construction completion. After each contractor has prepared completed construction documents and results of prior partial acceptances, the contractors have successively submitted to MRT Engineering Office, BOHSR for the initial inspection of final construction completion acceptance operations.
After receiving the initial acceptance documents from MRT Engineering Office for the final construction completion acceptance, BOHSR implemented the first acceptance operations on Mar. 30, 2017 and issued the “construction settlement acceptance certificate” to the contractor. The remaining tenders also submitted to BOHSR for acceptance operations after passing the initial acceptance process by MRT Engineering Office. The final construction acceptance operations for all civil engineering tenders are scheduled to be completed by the second half of 2017.