機場捷運CU02標土建工程部分驗收辦理情形 Summary on Partial Acceptance Process of the TIAA MRT CU02 Construction Tender
機場捷運CU02標部分驗收現場查驗

機場捷運CU02標位處桃園國際機場內,其部分工作範疇如「A12、A13、A14、A14a車站、華航緊急出口及明挖隧道段地面道路、景觀及設施等復舊工程」係為配合桃園國際機場公司辦理第三期航站大廈建設計畫前置作業,需先行移交該公司;另「第一航廈車道及雨庇代辦工程」,係屬民航局委託本局代辦交由CU02標之工作,依規定需於工程完成後移交委辦單位,故前述兩項工作需先行辦理部分驗收後,方能移交桃園機場公司及民航局接管並辦理後續作業。
CU02施工標承包商大陸公司於103年1月9日依據本局捷運工程處函示及契約規定提報本案兩項工程竣工及請求辦理部分驗收,經監造及捷運工程處分別召開二項工程之竣工確認會議,確認承包商已依契約規定完成。嗣經捷運工程處於103年2月24日核定工程竣工並陳報本局同意後,隨即辦理相關部分驗收作業,其中「A12、A13、A14、A14a車站、華航緊急出口及明挖隧道段地面道路、景觀及設施等復舊工程」已於103年3月14~17日辦理初驗並於103年4月21日完成複驗;另「第一航廈車道及雨庇代辦工程」則於103年3月18日辦理驗收,並於103年5月19~20日辦理複驗。

TIAA MRT CU02 Tender is located inside Taoyuan International Airport. Partial constructions including "A12, A13, A14, A14a Station, China Airlines emergency exit, ground surface road of C & C Tunnel sections, and recover constructions of landscape and facilities" were needed to hand over to Taoyuan Airport Corporation in coordination to its Third Period Terminal Building Construction Project preliminary work. "Terminal One Traffic Lane and Canopy Entrusted Construction" was entrusted to BOHSR by Civil Aeronautics Administration (CAA) which was included in CU02 Tender and was regulated to be handed over to the entrusted authority upon construction completion. Therefore, the two constructions must undergo partial acceptance before handed over to Taoyuan Airport Corporation and CAA respectively for subsequent process.
The CU02 Tender contractor Continental Engineering Corp. has reported construction completion and requested partial acceptance for the two constructions on Jan. 9 2014 according to instructions by MRT Engineering Office and contract regulations. After holding construction completion confirmation meetings by the supervision authorities and the MRT Engineering Office on the two constructions, the contractors' obligations were confirmed to be finished. The partial acceptance process was executed after Construction Completion was accepted by MRT Engineering Office on Feb. 24 2014 and approval by BOHSR. "A12, A13, A14, A14a Station, China Airlines emergency exit, ground surface road of C & C Tunnel sections, and recover constructions of landscape and facilities" constructions finished initial acceptance at Mar. 14-17 2014 and secondary acceptance on Apr. 21 2014; the "Terminal One Traffic Lane and Canopy Entrusted Construction" finished initial acceptance on Mar. 18 2014 and secondary acceptance on May. 19-20 2014.